Project Schedule

Project completion was originally expected in Spring 2012. However, through a coordinated effort with Lee County Department of Transportation, an additional 600 feet of underground utilities, traffic signalization and at-grade improvements have been shifted to the SR 82 Widening project from Lee County’s Colonial Boulevard Widening project. This shift of work lessens the impact to the traveling public by having one contractor coordinate all items of work in the SR 82 and Lee/Colonial Boulevard intersection. With the additional work, the current project completion was late Summer 2012.